"Construction Info"


Home
Current Projects
Construction Info
Arizona Avenue
Washington Street
Design Guidelines
Frequent Questions
Community Info
Contact Us
Resources/Links

PROJECT HOTLINE:   480.898.4100

This page provides the most up-to-date construction information related to the Arizona Avenue Improvements Project, Frye Road to Chandler Boulevard.  We will do our best to provide the most current information; however, please remember that construction schedules sometimes need to be adjusted due to weather, utility coordination, or various other factors.  If you would like to receive e-updates for the project, please click here to send us your e-mail address.  For questions or concerns related to the construction, please feel free to contact our project hotline at 480.898.4100 or e-mail us at info@ChandlersNewFrontDoor.com.  Thank you for your patience during this construction.

ARIZONA AVENUE (FRYE ROAD TO CHANDLER BOULEVARD) CONSTRUCTION INFORMATION:

Provided below is tentative information for the upcoming week for Arizona Avenue construction, Frye Road to Chandler Boulevard  (Posted July 18, 2010):

  •  Work continues in Arizona Avenue as part of the Arizona Avenue Improvements project.  The project is in the second phase of construction for work on the pedestrian area and curb lanes (please see phasing information at right). 

  •  Traffic control continues to be one lane in each direction, with traffic pushed to the center of Arizona Avenue from Frye Road to Chandler Boulevard.  This traffic configuration is in place as part of Phase 2 for removals and reconstruction of sidewalk, curb, street lighting, and landscaping on the outside areas of Arizona Avenue.  Once work is complete on the outside areas, work will begin on the inside (middle) lanes of Arizona Avenue in the project area.

  •  As a coordinating project, work on the Bus Rapid Transit (BRT) site is scheduled to begin in the next couple of weeks, with work beginning on the west side of Arizona Avenue, just south of Chandler Boulevard.  As currently scheduled, this work should be taking place within the existing traffic control. 

      Boston to Chandler Boulevard:

  • Removals of curb, gutter, sidewalk, landscape and fencing have taken place on Arizona Avenue, between Boston and Chandler Boulevard.

  •  Work is nearing completion on the joint trench for electric services between Boston and Chandler Boulevard.  This includes work across the Jack in the Box driveway with the trench (access will always be maintained), and ultimately removal and replacement of the Jack in the Box driveways, which will be accomplished one-half at a time to maintain access.

  • Tentatively scheduled to begin Wednesday, July 21st, crews will be working on Arizona Avenue at the Buffalo Street intersection for the joint trench to cross that intersection.  In addition, crews will be installing brick pavers behind the crosswalks on the east and west side of Buffalo Street.  To accommodate this construction activity, BUFFALO STREET WILL BE CLOSED ON THE WEST AND EAST SIDE OF ARIZONA AVENUE (both at the same time), beginning next Wednesday, July 21st, for approximately four weeks.  Arizona Avenue will continue to be open to north and southbound traffic, and access to the west and east side of Arizona Avenue will be open via Boston Street.  Message boards will be placed south of Boston Street and north of Buffalo Street alerting travelers to use Boston Street for business access, as Buffalo Street will be closed.  This work on Buffalo will be followed by similar work on Boston Street, but Buffalo and Boston will NOT be closed at the same time.

  • Crews continue to work on installing landscape irrigation sleeving, and the grading in the area where the sidewalk and curb and gutter was removed, to prepare the subsurface for forming and pouring of the curb and gutter on the west side of Arizona Avenue, from Boston to Chandler Boulevard. 

  • Crews continue work pouring curb and gutter and back concrete edge band (this sets the border on the back side for the brick pavers) on the west side of Arizona Avenue, from Buffalo to Chandler Boulevard.  Crews are also working this week and next to pour slurry from Boston to Buffalo, between the already-poured curb and gutter and back edge band.  This work will be followed by the forming and pouring of the cross bands (X's) on top of the slurry, between the curb and gutter and back edge band.  This all sets the "borders" for placement of the brick pavers in this area. 

  • Crews are also working this week on excavating for and pouring traffic signal foundations on the south side of Buffalo and the north side of Boston.

      Frye to Boston:

  •  Asphalt removals (not sidewalk removals) have taken place for the east side of Arizona Avenue, between Frye and Boston to work on the joint trench for electric services and landscape sleeving in that area.  The work is being scheduled to coordinate with the City Hall project site work taking place.

  • Tentatively scheduled for late next week, crews will work on asphalt removals (not sidewalk removals) on the west side of Arizona Avenue, between Frye and Boston to begin work on the joint trench, installation of street light pole foundations and pouring of catch basins in that area for the storm drain system.

  •  During construction, Arizona Avenue will remain open and should always have at least one lane in each direction in the corridor, except for possible coordinated weekend work when necessary in the intersection at Boston, Buffalo, or Frye.  In addition, there should always be left-turn access into the Square either via Buffalo or Boston. 

  •  For comments or concerns regarding the project, please feel free to e-mail or contact our project line at 480.898.4100.  

 

ARIZONA AVENUE IMPROVEMENTS CONSTRUCTION PHASING INFORMATION:

Improvements to South Arizona Avenue, Frye Road to Chandler Boulevard, are tentatively scheduled to begin March 8th and completed approximately November 2010.  Generally speaking, work will be daytime; however, temporary striping and traffic control equipment will be up 24 hours to maintain a safe construction zone.  Occasionally, night and weekend work may be more conducive to a specific activity, and that work will be coordinated and communicated in advance.  The project has been sequenced into four phases, with the following tentative construction schedule information:

PHASE 1: Utility Crossings (1.5 mos) -  Utility crossings are scheduled to begin in March as the first phase of construction.  Approximately 50 lateral lines (running east-west) will need to be installed under Arizona Avenue to make connections to the City’s storm drain, sewer, and water systems; and APS’ electric and power crossings for future traffic signals and street, pedestrian and landscape lighting.  During this phase, traffic will be restricted to one lane in each direction (north-south) with left turns scheduled to be permitted at Frye, Chicago, Boston and Buffalo.

PHASE 2: Pedestrian Area/Curb Lanes (3 mos)  -  As utility crossings are completed, crews will begin to remove existing sidewalk, curb, gutter, and the outside (curb) lanes of asphalt.  During this phase, we will coordinate with individual businesses directly on Arizona Avenue to coordinate access.  Traffic will continue to be restricted to one lane in each direction, traveling in the middle lanes, and left turns will be permitted when possible.  There will always be left turn access into the Square at Boston or Buffalo. Intersection work may require weekend work, and will be coordinated in advance.

PHASE 3: Inside Lanes/Medians (2.5 mos)  -  As work is completed on the future pedestrian areas and curb lanes, crews will move to the inside lanes to remove asphalt, work on the median islands on the north end, and work on the grade below the asphalt.  During this phase, traffic will continue to be restricted to one lane in each direction, traveling on the outside lanes, and left turns will be permitted when possible.   There will always be left turn access into the Square at Boston or Buffalo. 

PHASE 4: Final Milling and Overlay (.5 mo)  -  Once work is completed on Phase 3 (above), crews will mill (remove) asphalt to prepare for base course (bottom layer) and surface course (top layer) of asphalt.  This work will require various restrictions as the milling, and then paving operation moves in the corridor, usually working the curb lanes first, and then the inside lanes.  Once the surface course is completed, manholes and other utilities will need to be adjusted (raised) to be flush with the new asphalt, and then final striping will occur.  This process generally takes about two weeks to complete. 

 

 

Click here to download our FEB 2010 Construction Flyer

 

 

 

Phase 1 (1.5 mos):  Utility Work and Crossings

Phase 2 (3 mos):  Pedestrian Area/Curb Lanes

Phase 3 (2.5 mos): Inside Lanes/Median

Phase 4 (.5 mo): Final Milling and Overlay

     

Home | Current Projects | Construction Info | Arizona Avenue | Washington Street | Design Guidelines | Frequent Questions | Community Info | Contact Us | Resources/Links
City of Chandler Official Website
 
For problems or questions regarding this Web site contact [info@chandlersnewfrontdoor.com].
Last updated: 05/18/09.